Damascus
Master Plan Phases
Updated 12/19/05
PHASE
1 & 2:
Prepare Draft Purpose and Outreach Strategy Report and Community
Information Gathering Meetings. (July through November 2002)
PHASE
3:
Present to the Planning Board for approval of the Purpose and
Outreach Strategy Report. February 13, 2003
PHASE
4:
Identify alternative actions and Draft Master Plan recommendations.
Task Force Meetings. (March through December 2003)
Presentation
of Staff Draft Concept to Community; (January 2004)
Adjustments to Staff Draft if Needed. (January-May 2004)
PHASE
5:
Finalize the Staff Draft Master Plan; (January-May 2004)
The
M-NCPPC staff presented the recommendations of the Staff
Draft to the planning board on Thursday, September
30, 2004. An executive summary of the Staff Draft was presented
to the community on Wednesday, September 8, 2004.
PHASE
6:
Planning Board Public Hearing and Worksessions (October
2003 - February 2004) (November 2004 - July 2005)
The
Planning Board will review the Staff Draft Master Plan, make
any necessary revisions and will then publish the Planning
Board's Public
Hearing (Preliminary) Draft Plan.
Copies of the Planning Board's Public Hearing (Preliminary)
Draft Plan document were sent to the County Executive, County
Council, municipalities and members of the Master Plan Review
Committee. The Plan is available to the public.
After
the public hearing, the Board will hold open worksessions
to review the testimony and to determine whether to make any
revisions to the document.
*PHASE
7, 8, & 9:*
Executive Review, Council Review, Public Hearing, Worksessions
and Approval (March - November 2004). (October 2005 - May
2005) (January 2006-August 2006)
Once the
Planning Board has revised the Public Hearing Draft Plan,
it will be transmitted to the County Council and the County
Executive as the Planning Board's (Final) Draft Plan.
During
this phase, the County Council will hold a public hearing
at which anyone may testify, either orally or in writing.
At the close of the public hearing, the County Council will
hold open worksessions to determine if amendments to the Plan
submitted by the Planning Board are warranted. The plan will
then be approved or disapproved by the Council. If and when
the Council approves the plan, a Sectional Map Amendment (SMA)
will then be prepared to implement the zoning changes recommended
in the Plan. The SMA will also involve a formal public review
process, including a public hearing by the District Council
(Montgomery County Council).
PHASE
10:
Master Plan Monitoring
Once the
Master Plan is approved and adopted, Community-Based Planning
staff will continue to work in the master plan area, working
on the facilitation of master plan recommendations. In addition
to monitoring master plan facilitation issues on a regular
basis, Community-Based Planning staff will also engage in
a variety of implementation-related planning and regulatory
activities. Annual Master Plan Status Reports will be prepared
by the Community-Based Planning staff to monitor progress
in implementing the Plan's recommendations. The ongoing nature
of this phase will help to focus the attention and resources
needed to achieve the Plan's recommendations for Damascus.
* Current phase*